Tuesday, December 28, 2010

Tank Storage Erection: Summary Part 1.

The project took place in Pulau Indah for chemical plant expansion. The duration for the completion is around one year, starting with the piling and closed with a final inspection from BOMBA and the client. I only focused most on mechanical works above than other works.

So here it is.

Sorry I have to skip the civil works for tank foundation, since I don't have the pictures; it is all kept in the memory card which I sent to the main office. I told them to post it, but they didn't.

The civil works for tank foundation was mostly piling, and then followed with reinforcement bar, and finally the concreting. So, from here, let's move to the first picture.


Laying Bitumen to the tank foundation


Laying Bitumen to the tank foundation


Laying Bottom Plate


Shell Manhole opening


Shell Manhole opening


Pipe rack footing construction


Pipe rack footing construction - concreting


Shell plate installation in progress


Far view of works on site


Installation of pre-fabricated pipe support


Tank roof truss stacked together


Laying off 4" piping to the pipe support


General progress


Construction of pump shed footing


Pre-fabricated shell manhole


Construction of pump shed in progress


General works in progress


Hacking pavement for future underground electrical cable installation


Hacking pavement for installation of underground electrical cables.


Existing piping and cables underground


Bad weather should be recorded because it is intefering the work progress.


Pipe supports installed



Reinforcement plate ready for the shell manhole.
 

Site General View


Shell plate welding in progress for vertical and horizontal seams.


Tank storage


Concreting work in progress


Pump Shed floor slab concreting in progress.


Installation of roof truss in progress.


Excavation works for pipe footing installatin between tanks.


Installation of roof truss in progress.


Pre-fabrication of intertank walkway.


More progress for pump shed footing and plinth.


General view of the roof truss


General view of the roof truss.


Installation on spiral stairs.


Installation of gate valves at tank nozzles.


Installation of gate valves for tank nozzles.


General View.


General view of piping at the exchange hose area.


Installed spiral stairs.


Different view at the exchange hose area.


4 comments:

Anonymous said...

Storage Tank- Manufacturer, Supplier and Exporter of Storage tanks in Delhi, India provides water storage tanks, pressure vessel, hot water storage tanks, propane storage tanks, plastic water storage tanks, fuel storage tanks, cold water storage tanks and deals in all Delhi/NCR (Noida, Ghaziabad, Faridabad, Gurgaon and Chandigarh), India.

Richelle Loughney said...

That’s a large project to use so many storage tanks! Chemical plants do need a lot of storage tanks to store their chemicals and keep these from harming the surrounding area. For maximum safety, it is best for a chemical storage tank to be galvanized and have 3/16’ in multiple layers to prevent contamination.

remsauce said...

Initially the plant owner only want to build 7 numbers only. In the end, they decided to build smaller but practical tank storage up to 14 nos. It means that they can store wider selection of chemical liquids. Having completed this project sure does add more understanding to the mechanical engineering field.

Gene said...

We are the USA based manufacturer & supplier of water storage tanks, poly tanks & plastic tanks with more than 30 years of experience.

USA Water Tank Suppliers